Gatsibo residents wait nearly a year for electricity meters

Share with Others

Residents of Kabarore Sector in Gatsibo District, Eastern Province, are calling for faster electricity connections after waiting more than seven months for prepaid electricity meters, locally known as Cashpower.

The residents said electricity distribution works had begun in their area, including the installation of poles, power lines and household wiring, but many homes remained without electricity because the meters had not been installed.

In Simbwa Cell, some households have already been connected, while more than 250 others are still waiting for electricity meters.

Residents said they were frustrated by seeing electricity poles and wires installed near their homes but being unable to use electricity, despite waiting for months.

They said they had been assured that the meters would be provided, but had yet to receive a clear timeline for the connections. The delay, they added, was affecting their daily lives.

Mugabo Jackson, head of the Rwanda Energy Group (REG) branch in Gatsibo District, told Rwanda Broadcasting Agency (RBA) that the outstanding connections would be completed under a nationwide electricity distribution project.

“We have a nationwide electricity distribution project underway in Gatsibo, including Kabarore Sector. The work is at an advanced stage, with poles already installed. What remains is to connect the electricity,” he said.

“I would not say the meters are unavailable; rather, the process takes time. We ask residents to be patient, as they should have electricity within the next few days.”

The project, known as the EPC Contract, covers electricity distribution in Nyagatare and Gatsibo districts. It is expected to connect 39,000 households, including 22,000 in Gatsibo District.

The project is approximately 80 per cent complete and is scheduled for completion in 2027, at a cost of more than $18 million.

Across Rwanda, 15 cells reportedly remain without electricity, including some where infrastructure such as power poles has already been installed but households are still waiting to be connected.

Figures from the Ministry of Infrastructure show that 88.3 per cent of Rwanda’s population has access to electricity. Of these, 63.3 per cent are connected to the national grid, while 25 per cent rely on off-grid systems, mainly solar power.

The government is working to ensure universal access to electricity by 2030, including expanding the use of solar energy.